Receiving a semi-finished apartment in Egypt means taking over a unit that is structurally complete but missing its final finishes, and signing a handover record that states exactly what you accepted. Do not sign until you have checked the unit against the specification schedule in your contract, and write every defect into the record itself, with the date, instead of promising to "send a message later".
Quick answer: "Semi-finished" (nos tashteeb) is a market label, not a legal grade. Each developer defines it in the contract and the sales brochure. Before signing, check five things: contract match, plaster and levels, electrical and plumbing rough-in, waterproofing and damp, and external windows and doors. Record each finding in writing with dated photos.
Buying in the New Capital? Read our New Capital real estate due-diligence guide before you pay anything.
What "semi-finished" covers, and where definitions drift
Most Egyptian sellers describe a ladder: bare brick, plastered, semi-finished, then fully finished in several grades. The rungs are real, but their edges move. One developer's semi-finished unit may include complete electrical conduits; another's may only have the main risers. So the only reference that counts is the specification annex of your own contract.
The table below shows what typically sits on each side of the line. Treat it as a list of questions, not a promise from any developer:
| Item | Usually delivered | Usually left to the buyer |
|---|---|---|
| Walls | Plaster, sometimes a first coat of putty | Final paint |
| Floors | Levelled screed | Tile, porcelain or parquet |
| Electrical | Conduits and boxes, maybe cables | Sockets, switches, light fittings, final connections |
| Plumbing | Water and drainage rough-in | Sanitary ware, mixers, basins |
| Windows and doors | External windows, usually the entrance door | Internal room and kitchen doors |
| Ceilings | Concrete or plaster | Gypsum board and recessed lighting |
If your contract is silent on any row, ask the developer in writing before handover day. Silence is where disputes begin.
The paperwork to bring
A good inspection starts at your desk. Put this file together first:
- The contract and specification annex, printed, with finishing clauses, floor area and floor number highlighted.
- The approved unit plan, so you can measure rooms and see whether the real area is close to what you contracted.
- Payment receipts and a statement of the balance from the developer, so handover cannot become cover for charges you did not expect.
- The status of the maintenance deposit and any owners' association fee. We explain how this works in the maintenance deposit guide.
- A laser measure, torch, phone charger, pencil and a small spirit level, plus your phone camera.
If you can, bring a civil engineer or a finishing contractor who knows the area. Their fee is small beside the cost of a defect found after you have signed.
Walking the unit: an eight-point routine
Use the same order every time so nothing is skipped. Photograph each finding with the unit number in frame.
- Walls and plaster. Run your palm over the walls and tap lightly with a knuckle. A hollow sound suggests plaster has lifted off the brick. Separate hairline surface cracks, which are common, from a deep crack running from a window corner to the ceiling, which deserves an engineer's opinion.
- Straightness and levels. Hold a spirit level or a long straightedge against walls and floors. A visible slope now will show up under the tiles later.
- Ceilings. Look for damp patches or stains from the floor above or from light wells.
- Electrical rough-in. Count boxes and points room by room against the plan and contract. Make sure the distribution board is present and not left open.
- Plumbing and drainage. Ask whether the pipes were pressure-tested. Open the water supply if it is on and watch the joints. Pour water into floor drains and see where it runs.
- Bathrooms and kitchen. Falls toward the drain matter a great deal. A spot where water sits is a future problem under the tiles.
- Windows and balconies. Open and close everything. Check glass, handles and seals. A balcony floor should never slope toward the inside.
- Entrance door and ventilation. Test the lock and hinges, then the vents and shafts in the kitchen and bathrooms.
If the unit sits in a new compound, ask also whether roads, utilities and security are actually operating. Getting the keys to a unit says nothing about the services around it. For New Capital projects, see newcapital.site.
Minor snag or reason not to sign?
Not every defect justifies postponing handover, and not every defect can wait. A workable triage:
| Severity | Examples | Suggested action |
|---|---|---|
| Minor | Scratch on the entrance door, a small plaster patch | Log it in the record with a repair deadline |
| Moderate | Fewer electrical points than the plan, a mild floor slope | Write that it deviates from the contract and ask for a dated written schedule |
| Serious | Active damp, a long crack, a leaking drain, area below the contract figure | Do not sign final acceptance before an engineer's opinion and a written reply from the developer |
What you leave unwritten is hard to prove later. What you write clearly and date becomes the basis of your claim.
The handover record: what to write
- Date, unit number, and the name and role of the person handing over.
- Each defect described precisely: "crack about one metre long on the master bedroom wall beside the window", not "defects exist".
- If you are not satisfied, write "provisional acceptance subject to the attached remarks" in place of "final acceptance".
- A signed, stamped copy that you photograph on the spot.
- Never sign a blank or incomplete form to be filled in later.
If the developer will not record your remarks, put your objection in a formal written notice. The Consumer Protection Agency publishes information on consumer rights and complaints, and you should speak to a lawyer before any legal step. This article is general information, not legal advice.
After handover, before the first worker arrives
- Document the unit's condition with full photography before any contractor enters, so handover defects are not confused with fit-out damage.
- Collect written quotations from more than one contractor, then plan the work using our guide to apartment finishing stages.
- Understand each finishing grade before you compare offers. Our explainer on finishing levels in Egypt lays them out.
Bought on the resale market? Read resale versus buying from the developer too, because a previous owner's obligations can travel with the unit. Our viewing checklist covers the earlier visits.
How Buildoura fits
Buildoura does not inspect your apartment for you, and it is better to say so plainly. What the platform does is let brokers and developers publish units with their specifications, finishing status and photos on a site of their own, so the written detail reaches you before the viewing, not after. Ask any seller to put the finishing clause in writing, and to show it in the listing the same way it appears in the contract.
FAQ
Can I refuse to take over a semi-finished apartment if I find defects?
That depends on your contract wording and how serious the defect is. In practice, avoid signing final acceptance, list the defects in the record and ask for a written reply with a repair date. Have a lawyer read your contract before any formal step.
What is the difference between semi-finished and plastered only?
Plastered only means the walls have plaster and little else. Semi-finished usually goes further, to rough-in work, levelled floors or external doors, but the line differs by developer. Get the finishing items in writing and compare them with what you see.
Do I need an engineer to take over a semi-finished unit?
It is not compulsory, but it helps with cracks, damp and the plumbing and electrical rough-in. An engineer can save you costly repairs after you sign. If you cannot bring one, at least work through the eight-point routine above.
Is the maintenance deposit part of the handover paperwork?
It is often requested at or before handover, though practice varies by project. Ask the developer how much it is, who collects it and whether a previous owner already paid it.
When should I start finishing work after handover?
After you have documented the unit, resolved serious defects and collected written quotations. Starting early over an unfixed leak or crack can mean tearing out finishing work you have already paid for.
Written by: Hala Mostafa, Real-Estate Solutions Lead at Buildoura.